Experience

Vision Energy has vast wind energy development and construction experience in the Midwestern United States. Vision Energy primarily originates and develops its own wind projects from conception through completion and long-term operation. With this long-term perspective, Vision Energy takes a proactive approach to building strong relationships with various project stakeholders including landowners, local communities, government agencies, interconnecting utilities, power purchasers, equipment manufacturers and contractors.

In 2003, Vision Energy initiated and co-developed wind farms in several states. Two of these wind farms began construction in 2007: the 150 mega-watt (MW) Camp Grove Wind Farm in Stark and Marshall Counties, Illinois, and the 130MW Benton Wind Farm in Benton County, Indiana.


Camp Grove Wind Farm

Owner: Camp Grove Wind Farm LLC
Location: Stark & Marshall Counties, IL
Size: 150MW (100 1.5MW GE, sle rev4)
Acreage: 13,500 acres
EPC Contractor: M.A. Mortenson
Co-Developer: Orion Energy Group, LLC
Construction Start: April 15, 2007
Operational Date: December 15, 2007
O&M Partner: enXco

Slideshows: Foundations, Cabling

Press:
Stark County News
August, 2003
PJ Star
November, 2005
M.A. Mortenson selected as EPC
January, 2007
O&M company selected by CGWF
February, 2007
Wind Farm Helps Sheriff
November, 2007
Benton County Wind Farm

Owner: Benton County Wind Farm LLC
Location: Benton County, IN
Size: 130MW (87 1.5MW GE, sle rev4)
Acreage: 9,250 acres
Co-Developer: Orion Energy Group, LLC
Construction Start: August 15, 2007
Operational Date: April 15, 2008
Power Buyer: Duke Energy of Indiana, Inc.

Press:
Journal & Courier
September, 2007
Indy Star
June, 2006
Cincinnati Enquirer
February, 2006
Duke to buy Power
August, 2006
Fowler Ridge Wind Farm

Owner: Fowler Ridge Wind Farm LLC (BPAE and Dominion)
Location: Benton County, IN
Size: Phase 1 - 400MW (182 1.65MW Vestas, 40 Clipper 2.5MW)
Size: Phase 2 & 3 - Up to 1,000MW
Acreage: 54,000 acres
Co-Developer: Orion Energy, LLC
Construction Start: February, 2008
Operational Date: December, 2008
Power Buyer: AEP, Dominion